Week 1 was mostly demo

Week 2 was dedicated to reinforcing the roof structure, most of the wiring. 

Week 3 we finished the wiring and prepped the ceiling for drywall. Then things stalled a bit because the insulation guy had an equipment problem. 

Now, week 4, we got the insulation done on Monday, and drywall is under way. The new front door arrived, and the light fixtures are all picked out. It’s definitely moving along. 