Progress
Week 2 was dedicated to reinforcing the roof structure, most of the wiring.
Week 3 we finished the wiring and prepped the ceiling for drywall. Then things stalled a bit because the insulation guy had an equipment problem.
Now, week 4, we got the insulation done on Monday, and drywall is under way. The new front door arrived, and the light fixtures are all picked out. It’s definitely moving along.
And then there were two

As a former restaurant, we had 4 propane tanks all lined up in front of the house. We don’t use as much hot water or heat as a restaurant, and we’ve converted a lot of our appliances to electric anyway, plus the pellet stove.
So, we convinced the gas company to haul away two of the tanks, giving us another few feet of usable space ( or at least beautifiable space ) in front.
some of our heating
And now this
Vacations are great, but it’s also great to be home. And so, on to the next chapter…


The home I returned to is a wreck, but that’s a good thing. The long-delayed next phase of the remodel is fully underway, with all of the walls and ceiling in the living and dining room torn apart, waiting for new insulation, rewiring, and so on. Lee moved all the furniture out into Chuck’s garage, except for a very cozy little set up in the kitchen.
It will be very exciting to have the upstairs completely done, which should be about another four weeks from now.